The traditional two-week report on the latest works on the construction site of the business-class residential complex “Crystal Avenue” in Petropavlivska Borshchahivka.
At the second stage (11-A, Oksamytova St.,) plumbing works have been performed on the 14th floor inclusive. Windows have been installed on 10-12 floors. The Internet is being conducted (5-6 floors). Electrical work has been started (performed on 2–6 floors) and plastering of walls and slopes (performed on 2–4 floors).
At the third stage (1-A, Kryshtaleva St.,) facade works on 8-11 floors continue. Plumbing and floor screed have been completed. Installation of the first of the two elevators, waterproofing of balconies in public places and finishing works in public places (3-4 floors) have begun.
At the fourth stage (1, Kryshtaleva Street) works on the monolithic frame on the 10th floor have been completed.
The construction of the second part of the underground parking lot is also underway. Slab reinforcement work is currently underway there.
You can find out details about buying an apartment in the business class residential complex “Crystal Avenue” or see how the construction of the complex is going on by visiting the sales department of our residential complex: 14 – A, Soborna st., Petropavlivska Borshchahivka vil.
Phones: 044 499 25 67; 067 663 89 35.