Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
80%

Progress in construction RC "Crystal Avenue", December 2024

The first stage (9-A Oksamytova St.)

•  the house is commissioned.

The second stage (11-A Oksamytova St.)

•  the house is commissioned.

The third stage (1-A Kryshtaleva str.)

•  the house is commissioned.

Fourth stage (1 Kryshtaleva str.) 

•  the process of house commissioning and connecting the gas supply is ongoing.

The fifth stage (1-B Kryshtaleva str.)

•  installation of internal gas supply systems, plastering and screed arrangement are completed;

•  facade works (90% complete), interior finishing and electrical works, and elevator installation are in progress;

•  apartment doors have been ordered;

•  waterproofing works are underway in the last part of the underground parking lot.