Herein we keep telling about the construction progress of the RC "Crystal Avenue" in Petropavlivska Borshchahivka.
In the second phase (11-A, Oksamytova St.) the connection of power supply networks and works on the improvement of the territory are ongoing.
In the fourth phase (1, Kryshtaleva St.) installation of a ventilated facade (%95 ready), installation of a wet facade (%95 ready), gasification of the house (%90 ready), installation of fire equipment (%90 ready), landscaping works are in progress. All doors are installed in cold passages. Preparation for the laying of power cables is ongoing.
In the fifth phase (1-B, Kryshtaleva St.) bricklaying of the walls on the 12th floor is in progress.