In November 2017, RC “Crystal Avenue” announced itself by making first apartment sales at Oksamytova St., 9-A. The construction had just started, so the first investors could purchase residential property at the earliest stages of the building’s erection.
As of today, the building’s façade is over 70% ready. Air ventilation systems are fully installed; we started installation of mood lighting, that will set its own inimitative night style to RC “Crystal Avenue”.
The central entrance of the building is open, the construction of the spacious hallway can be seen there. The outlines of future reception and leisure zone are already revealed. Venting and fireproof systems are 80% ready; installation of high-speed elevators is close to its completion.
Staircase flights are fully tiled. The walls of stairwells and public spaces are varnished in order to protect from physical impact and to give homelike touch.
Heating units installation and glass units adjustment are in progress. Gas pipework routing is 70% ready.
Underground parking is completely moisture resistant. The installation of electric equipment is being performed there.
During the sales period, the cost of square meters of apartments in this house increased by 18%. People who want to make good realty investments, still can purchase an apartment in a second phase construction project. This building is at Oksamytova St., 11-A; at the moment we are performing construction of walls at the ground floor using cast-in-place technology.
Make a good investment! Come to our Sales Department: Petropavlivska Borshchagivka, Soborna St., 14-A. And don’t hesitate to call us at the following numbers: (044) 499-2599; (067) 663-9452.