REPORT FROM THE CONSTRUCTION SITE OF THE BUSINESS CLASS RC “CRYSTAL AVENUE” (PETROPAVLIVSKA BORSHCHAHIVKA)

07.12.2020

Construction of the residential complex “Crystal Avenue” from NovaBudova continues. Read on at what stage the construction of each of the houses is.

In the second phase (11-A, Oksamitova St.,) roofing works are being carried out. The floor screed has been made on the 10th floor. Windows installation is complete.

In the third phase (1-A, Kryshtaleva Street) the installation of doors has been completed. Facade works, and also installation of drainpipes and guards proceed.

In the fourth phase (1, Kryshtaleva Street) monolithic-frame works at the level of the 15th floor continue. Brick masonry has begun. Today this type of work has been performed at the level of the 5th floor.

In the fifth phase (1-B, Kryshtaleva Street) the development of the foundation pit has been completed.

The construction of the second part of the underground parking lot is also underway. The overlap is currently being completed there.