Herein we tell you about the progress of construction work in the business class residential complex “Crystal Avenue” in Petropavlivska Borshchahivka.
In the second phase (11-A, Oksamytova St.) installation of balconies on the upper floors and starting-up of elevators have been completed. Improvement of the adjacent territory and public usage places arrangement continues (installation of windows is completed and facade works are started).
In the fourth phase (1, Kryshtaleva St.) plastering works (except for the 1st floor) and heating installation (except for the 15th-17th floors) are almost completed. Work on the floor cap (on the 13th floor) continues.
In the fifth phase (1 – B, Kryshtaleva St.) monolithic frame works on the 11th floor are underway. Brickwork start (on the 2nd floor).
The second part of the underground parking lot construction is also underway. The floor cap is completed there. Work on the installation of fire protection systems and electrical work is underway.
You can sign up for viewing or find out details about the availability of apartments in the sales department by phone: 044 499 25 67; 067 663 89 35.
Address of the RC “Crystal Avenue” sales department: 14 – A, Soborna street, Petropavlivska Borshchahivka.