THE RC “CRYSTAL AVENUE” CONSTRUCTION: WORK PROCESS AND GIFT CERTIFICATES FROM NOVABUDOVA

09.11.2021

Here we tell you about the progress of construction work in the business class residential complex “Crystal Avenue” in Petropavlivska Borshchahivka.

In the second phase (11-A, Oksamytova St.) the installation of balconies on the upper floors and start-up and adjustment works in the elevators are almost completed. The common spaces are also under construction.

In the third phase (1-A,  Kryshtaleva St.) the installation of the playground is almost completed.

In the fourth phase (1, Kryshtaleva St.) plastering works are almost completed (except for 1, 16, 17 floors). Roof insulation has been completed. Installation of heating (on 15-16 floors) and work on a floor cap (on 10-11 floors) proceeds.

In the fifth phase (1 – B, Kryshtaleva St.) monolithic frame works on the 9th floor are underway.

The construction of the second part of the underground parking lot is also underway. There are ongoing works on the installation of fire protection systems, electrical work and a floor cap.