At the first stage (9-A, Oksamytova Street), which has already been commissioned and inhabited, preparatory earthworks for the construction of the second part of the underground parking lot have begun.  We'd like to add that the parking lot sale in the underground parking will begin very soon!

At the second stage (11-A, Oksamytova Street) works on monolithic frame of the 14th floor have been completed.  The brickwork of the external walls of the 11th floor and the installation of monolithic stairs at the level of the 10th floor are in progress.

At the third stage (1-A, Kryshtaleva Street) monolithic works and brickwork of walls have already been completely executed.  Builders are currently installing windows on the 10th floor.  Finishing works are also underway: now the masters are plastering the walls on 5-6 floors and continuing the electrical work.

At the fourth stage (1, Kryshtaleva Street) works on monolithic frame of the 4th floor level are underway.