THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE" CONSTRUCTION: MONTHLY DIGEST (FEBRUARY 2024)

16.02.2024

Herein we are telling you about the construction of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.

In the second phase (11-A, Oksamytova St.), small architectural forms (trash bins, benches) have been installed. Preparation for the installation of the children's playground is underway.

In the fourth phase (1, Kryshtaleva St.), installation of equipment in the control room and doors on the 1st floor has been completed. Work on the decoration of the public usage places is ongoing (55% complete), commissioning of the elevator equipment, facade work on the 1st floor (60% complete).

In the fifth phase (1 – B, Kryshtaleva St.), the brickwork of the walls has been completed. Installation of windows is in progress.

You can find out details about the construction, terms of purchasing an apartment or promotional offers by phone: +380960230310.