Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
80%
5
stage
40%

Progress in construction RC "Crystal Avenue", December 2020

First building (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• monolithic works in the second part of the underground parking lot have been completed.

Second building (11-A, Oksamytova Street)

• roofing works are carried out;

• floor screed has been made on the 10th floor;

• installation of windows is completed;

• plumbing work is carried out (performed on 2-9 floors).

Third building (1-A, Kryshtaleva Street)

• installation of doors is completed;

• facade works are underway (insulation and reinforcement of the wet facade has been completed);

• installation of drain pipes and guards for conditioners proceeds;

• finishing works in public places are underway

Fourth building (1, Kryshtaleva Street)

• monolithic frame works are underway at the level of the 16th floor;

• brickwork on the 7th floor continues;

• work on chimneys and air ducts continues.

Fifth turn (1-B, Kryshtaleva Street)

• borepiles have been installed