First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed.
Second phase (11-A, Oksamytova Street)
• work on connecting power supply networks and preparation for greening of the surrounding area continues;
• the arrangement of retaining walls and the work on the paving of passageways has been completed.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of a ventilated facade (100% ready);
• installation of a wet facade (98% ready);
• gasification of the house (90% ready);
• installed cooling of cold transitions;
• work on the improvement of the territory is ongoing;
• public usage places decoration (5% ready) and production of public usage places doors started;
• preparation for the stair railings installation is underway.
Fifth phase (1-B, Kryshtaleva Street)
• brickwork of walls on the 13th and 18th floors and the roof;
• installation of ventilation channels is completed;
• preparation for installation of windows is in progress.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: SEPTEMBER 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.09.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (SEPTEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.09.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.
26.09.2025