Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", January 2021

 

First phase (9-A, Oksamytova Street)

• the house is put into operation;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• performance of waterproofing works and preparation for backfilling in the second part of the underground parking lot.

Second phase (11-A, Oksamytova Street)

• the retaining wall has been completed;

• works on arrangement of the road to the first house of the RC are being conducted near the house.

Third phase (1-A, Kryshtaleva Street)

• elevators installation is completed;

• finishing works in public places are underway

Fourth phase (1, Kryshtaleva Street)

• monolithic frame works are underway on the level of the 16th floor;

• brickwork on the 7th floor continues.

Fifth phase (1-B, Kryshtaleva street)

• drilling piles are being made.