Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", November 2021

First phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• works on arrangement of fire-prevention systems, electric installation works proceed; completed floor cap in the second part of the underground parking lot.

Second phase (11-A, Oksamytova Street)

• start-up and adjustment works in elevators are finished;

• the arrangement of public usage places continues (installation of windows is completed and facade works are started);

• improvement of the adjacent territory continues;

• installation of balconies on the upper floors has been completed.

Third phase (1-A, Kryshtaleva Street)

• the house is commissioned;

• the arrangement of the adjacent territory around the house has been partially completed.

Fourth phase (1, Kryshtaleva Street)

• plastering works are almost finished (except for the 1st floor);

• roof insulation is completed;

• heating installation is almost completed (except for 15-17 floors);

• work on the floor cap (on the 13th floor) continues.

Fifth phase (1-B, Kryshtaleva Street)

• monolithic frame works on the 9th floor are underway;

• brickwork has been started (on the 2nd floor).