First phase (9-A, Oksamytova Street)
• the house is put into operation;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• performance of waterproofing works and preparation for backfilling in the second part of the underground parking lot.
Second phase (11-A, Oksamytova Street)
• the retaining wall has been completed;
• works on arrangement of the road to the first house of the RC are being conducted near the house.
Third phase (1-A, Kryshtaleva Street)
• elevators installation is completed;
• finishing works in public places are underway
Fourth phase (1, Kryshtaleva Street)
• monolithic frame works are underway on the level of the 16th floor;
• brickwork on the 7th floor continues.
Fifth phase (1-B, Kryshtaleva street)
• drilling piles are being made.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026