First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed.
Second phase (11-A, Oksamytova Street)
• installation and automation of barriers has been completed;
• installation of the parking lot access system is almost complete.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of air conditioning baskets and installation of the doors of the MCC was completed;
• work on the finishing of the public usage places (40% complete) is underway, installation of apartment doors (50% complete), installation and commissioning of elevator equipment, and installation of equipment in the control room.
Fifth phase (1-B, Kryshtaleva Street)
• brickwork of the walls is nearing completion (98% complete);
• installation of windows (10% complete) and sewerage systems are in progress.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025