Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", December 2023

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• installation and automation of barriers has been completed;

• installation of the parking lot access system is almost complete.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of air conditioning baskets and installation of the doors of the MCC was completed;

• work on the finishing of the public usage places (40% complete) is underway, installation of apartment doors (50% complete), installation and commissioning of elevator equipment, and installation of equipment in the control room.

Fifth phase (1-B, Kryshtaleva Street)

• brickwork of the walls is nearing completion (98% complete);

• installation of windows (10% complete) and sewerage systems are in progress.