Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", September 2021

First phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed

• works on arrangement of fire-fighting systems and electrical installation works in the second part of the underground parking lot have started.

Second phase (11-A, Oksamytova Street)

• start-up and adjustment works take place in elevators

• the membrane is being installed on the roof;

• finishing works of common usage areas are underway (installation of cold transition fences).

Third phase (1-A, Kryshtaleva Street)

• installation of a playground continues;

• laying of paving slabs is completed;

• installation of balcony railings in apartments has been completed.

Fourth phase (1, Kryshtaleva Street)

• plastering works are underway (on 15-16 floors);

• installation of heating continues (on 8-9 floors);

• work on the floor cap (on 6-7 floors).

Fifth phase (1-B, Kryshtaleva Street)

• works on monolithic frame on the 5th floor are underway.