The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• installation of the playground flooring has been completed
• the process of commissioning the house and connecting the gas supply is underway.
The fifth stage (1-B Kryshtaleva str.)
• installation of apartment doors and elevators has been completed;
• facade works are in progress (95% complete), finishing of the public usage places and staircases (65% complete), installation of technical doors (90% complete), installation of window and door structures on the 1st and 2nd floors (30% complete);
• commissioning works, installation of boilers and radiators, and landscaping works have begun;
• the waterproofing process has been completed in the last part of the underground parking lot; landscaping works, preparations for flooring and installation of the fire safety system are ongoing.