The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• installation of the playground flooring has been completed
• the process of commissioning the house and connecting the gas supply is underway.
The fifth stage (1-B Kryshtaleva str.)
• installation of apartment doors and elevators has been completed;
• facade works are in progress (95% complete), finishing of the public usage places and staircases (65% complete), installation of technical doors (90% complete), installation of window and door structures on the 1st and 2nd floors (30% complete);
• commissioning works, installation of boilers and radiators, and landscaping works have begun;
• the waterproofing process has been completed in the last part of the underground parking lot; landscaping works, preparations for flooring and installation of the fire safety system are ongoing.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.