Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
80%

Progress in construction RC "Crystal Avenue", March 2025

The first stage (9-A Oksamytova St.)

•  the house is commissioned.

The second stage (11-A Oksamytova St.)

•  the house is commissioned.

The third stage (1-A Kryshtaleva str.)

•  the house is commissioned.

Fourth stage (1 Kryshtaleva str.) 

•  installation of the playground flooring has been completed

•  the process of commissioning the house and connecting the gas supply is underway.

The fifth stage (1-B Kryshtaleva str.)

•  installation of apartment doors and elevators has been completed;

•  facade works are in progress (95% complete), finishing of the public usage places and staircases (65% complete), installation of technical doors (90% complete), installation of window and door structures on the 1st and 2nd floors (30% complete);

•  commissioning works, installation of boilers and radiators, and landscaping works have begun;

•  the waterproofing process has been completed in the last part of the underground parking lot; landscaping works, preparations for flooring and installation of the fire safety system are ongoing.