First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the local area around the house is partially completed;
Second phase (11-A, Oksamytova Street)
• interior finishing is done, installation of suspended ceilings, installation of lamps and fire detectors;
• hall finishing is in progress (30% ready);
• construction of the adjacent territory is in progress.
Third phase (1-A, Kryshtaleva Street)
• house is commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of a ventilated facade (50% performed);
• installation of the wet facade (40% performed);
• arrangement of internal gas supply (50% performed);
• arrangement of the roof is partially completed (70% ready).
Fifth phase (1-B, Kryshtaleva Street)
• monolithic works on the 17th floor have been completed;
• brickwork of walls has been completed on the 9th floor.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.