First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the local area around the house is partially completed;
Second phase (11-A, Oksamytova Street)
• interior finishing is done, installation of suspended ceilings, installation of lamps and fire detectors;
• hall finishing is in progress (30% ready);
• construction of the adjacent territory is in progress.
Third phase (1-A, Kryshtaleva Street)
• house is commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of a ventilated facade (50% performed);
• installation of the wet facade (40% performed);
• arrangement of internal gas supply (50% performed);
• arrangement of the roof is partially completed (70% ready).
Fifth phase (1-B, Kryshtaleva Street)
• monolithic works on the 17th floor have been completed;
• brickwork of walls has been completed on the 9th floor.
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: MARCH 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
28.03.2026
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: MARCH 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
18.03.2026