Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", January 2023

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the local area around the house is partially completed;

Second phase (11-A, Oksamytova Street)

• hall decor works are in progress (60% ready);

• works on connecting power supply networks are underway.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• partially completed arrangement of the adjacent territory around the house.

Fourth phase (1, Kryshtaleva Street)

• installation of a ventilated facade (70% performed);

• installation of the wet facade (65% performed); 

• arrangement of the roof is done. 