Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", January 2024

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• plants were planted;

• a fence was installed;

• installation of the parking lot access system was completed.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of apartment doors and elevator equipment has been completed;

• work on finishing the public usage places(40% complete) is underway, commissioning the elevator equipment, and installing equipment in the control room.

Fifth phase (1-B, Kryshtaleva Street)

• brickwork of the walls is nearing completion (98% complete);

• installation of windows continues (10% complete) and sewerage systems are being arranged.