Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", August 2023

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed;

Second phase (11-A, Oksamytova Street)

•works on connection of power supply networks, improvement of the territory are ongoing.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of a ventilated facade (%95 ready);

• installation of a wet facade (%95 ready);

• gasification of the house (%90 ready);

• installation of fire equipment (%90 ready);

• work on the improvement of the territory is ongoing;

• all doors in cold passages are installed;

• preparations for laying power cables are underway.

Fifth phase (1-B, Kryshtaleva Street)

• brickwork on the 12th floor.