First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed;
Second phase (11-A, Oksamytova Street)
•works on connection of power supply networks, improvement of the territory are ongoing.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of a ventilated facade (%95 ready);
• installation of a wet facade (%95 ready);
• gasification of the house (%90 ready);
• installation of fire equipment (%90 ready);
• work on the improvement of the territory is ongoing;
• all doors in cold passages are installed;
• preparations for laying power cables are underway.
Fifth phase (1-B, Kryshtaleva Street)
• brickwork on the 12th floor.
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: MARCH 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
28.03.2026
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: MARCH 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
18.03.2026