First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the local area around the house is partially completed;
• it is planned to commission the second part of the underground parking by the end of September.
Second phase (11-A, Oksamytova Street)
• interior finishing on the floors (work is completed on 15 floors);
• facade arrangement of the basement floor (600 sq. m. is ready);
• installation of suspended ceilings: 15 floors are completed;
• installation of radiators and installation of tiles on cold transitions is completed;
• 95% of the installation of lamps, fire detectors, pump, panel, hall decoration, water supply to the building is completed;
• landscaping of the surrounding area (30% ready).
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• the adjacent territory around the house arrangement is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of ventilated facade (30% ready);
• installation of wet facade (20% ready);
• arrangement of internal gas supply (50% ready);
• it is planned to complete the arrangement of the roof by the end of the month.
Fifth phase (1-B, Kryshtaleva Street)
• brickwork continues (completed on the 8th floor).
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025