Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", Вересень 2022

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the local area around the house is partially completed;

• it is planned to commission the second part of the underground parking by the end of September.

Second phase (11-A, Oksamytova Street)

• interior finishing on the floors (work is completed on 15 floors);

• facade arrangement of the basement floor (600 sq. m. is ready);

• installation of suspended ceilings: 15 floors are completed;

• installation of radiators and installation of tiles on cold transitions is completed;

• 95% of the installation of lamps, fire detectors, pump, panel, hall decoration, water supply to the building is completed;

• landscaping of the surrounding area (30% ready).

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• the adjacent territory around the house arrangement is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of ventilated facade (30% ready);

• installation of wet facade (20% ready);

• arrangement of internal gas supply (50% ready);

• it is planned to complete the arrangement of the roof by the end of the month.

Fifth phase (1-B, Kryshtaleva Street)

• brickwork continues (completed on the 8th floor).