First phase (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
Second phase (11-A, Oksamytova Street)
• installation of apartment and vestibule doors has finished;
• facade and finishing works, installation of elevators proceed.
• finishing works of common areas are underway.
Third phase (1-A, Kryshtaleva Street)
• improvement of the adjacent territory continues (laying of paving slabs and a playground installation);
• installation of balcony railings in apartments is coming to an end.
Fourth phase (1, Kryshtaleva Street)
• installation of window frames is completed;
• plastering works are underway (on the 10th floor);
• heating installation is underway (5-6 floors ready);
• floor cap work has started (2-3 floors).
Fifth phase (1-B, Kryshtaleva Street)
• the floor slab of the third floor is being prepared.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025