First phase (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
Second phase (11-A, Oksamytova Street)
• installation of apartment and vestibule doors has finished;
• facade and finishing works, installation of elevators proceed.
• finishing works of common areas are underway.
Third phase (1-A, Kryshtaleva Street)
• improvement of the adjacent territory continues (laying of paving slabs and a playground installation);
• installation of balcony railings in apartments is coming to an end.
Fourth phase (1, Kryshtaleva Street)
• installation of window frames is completed;
• plastering works are underway (on the 10th floor);
• heating installation is underway (5-6 floors ready);
• floor cap work has started (2-3 floors).
Fifth phase (1-B, Kryshtaleva Street)
• the floor slab of the third floor is being prepared.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: SEPTEMBER 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.09.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (SEPTEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.09.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.
26.09.2025