
The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• the process of connecting gas and electricity supply on a permanent basis is underway.
The fifth stage (1-B Kryshtaleva str.)
• facade works (98% complete), finishing of the public usage places and staircases (65% complete), installation of technical doors (95% complete), installation of window and door structures on the 1st and 2nd floors (60% complete), interior and electrical works (80% complete), installation of boilers and radiators (20% complete), and landscaping works are underway;
• commissioning works have begun;
• in the last part of the underground parking lot, landscaping works are underway, preparations for flooring and installation of a fire safety system are underway
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026