The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• the process of connecting gas and electricity supply on a permanent basis is underway.
The fifth stage (1-B Kryshtaleva str.)
• facade works (98% complete), finishing of the public usage places and staircases (65% complete), installation of technical doors (95% complete), installation of window and door structures on the 1st and 2nd floors (60% complete), interior and electrical works (80% complete), installation of boilers and radiators (20% complete), and landscaping works are underway;
• commissioning works have begun;
• in the last part of the underground parking lot, landscaping works are underway, preparations for flooring and installation of a fire safety system are underway