Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
80%

Progress in construction RC "Crystal Avenue", April 2025

The first stage (9-A Oksamytova St.)

•  the house is commissioned.

The second stage (11-A Oksamytova St.)

•  the house is commissioned.

The third stage (1-A Kryshtaleva str.)

•  the house is commissioned.

Fourth stage (1 Kryshtaleva str.) 

•  the process of connecting gas and electricity supply on a permanent basis is underway.

The fifth stage (1-B Kryshtaleva str.)

•  facade works (98% complete), finishing of the public usage places and staircases (65% complete), installation of technical doors (95% complete), installation of window and door structures on the 1st and 2nd floors (60% complete), interior and electrical works (80% complete), installation of boilers and radiators (20% complete), and landscaping works are underway;

•  commissioning works have begun;

•  in the last part of the underground parking lot, landscaping works are underway, preparations for flooring and installation of a fire safety system are underway