Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
80%
5
stage
40%

Progress in construction RC "Crystal Avenue", September 2020

First stage (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and partially occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• concrete preparation for the construction of the second part of the underground parking lot has been performed.

Second stage (11-A, Oksamytova Street)

• brickwork of the outer walls of the 15th floor has been made;

• plumbing work continues (ready to the 12th floor);

• windows are installed on 2-9 floors;

• installation of a fire system (2–6 floors), intercoms (2–4 floors) and the Internet installation 2–4 (floors) is underway.

Third stage (1-A, Kryshtaleva Street)

• roofing works are completed;

• facade works are underway (ready 3-7 floors);

• plumbing work is completed and floor installation work is almost completed.

Fourth stage (1, Kryshtaleva Street)

• works on a monolithic frame on the 9th floor are underway