First building (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• monolithic works in the second part of the underground parking lot have been completed.
Second building (11-A, Oksamytova Street)
• roofing works are carried out;
• floor screed has been made on the 10th floor;
• installation of windows is completed;
• plumbing work is carried out (performed on 2-9 floors).
Third building (1-A, Kryshtaleva Street)
• installation of doors is completed;
• facade works are underway (insulation and reinforcement of the wet facade has been completed);
• installation of drain pipes and guards for conditioners proceeds;
• finishing works in public places are underway
Fourth building (1, Kryshtaleva Street)
• monolithic frame works are underway at the level of the 16th floor;
• brickwork on the 7th floor continues;
• work on chimneys and air ducts continues.
Fifth turn (1-B, Kryshtaleva Street)
• borepiles have been installed
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.