Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", June 2021

First phase (9-A, Oksamytova Street)

• the house is commisisoned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• the walls are ready and the work on the entrance groups at the entrance to the second part of the underground parking lot is underway;

Second phase (11-A, Oksamytova Street)

• work on communications has been completed;

• floor cap has been made;

• facade works are underway.

Third phase (1-A, Kryshtaleva Street)

• installation of radiators and work on entrance groups is completed;

• completed work on input groups;

• finishing works in the lobby on the ground floor have been completed;

• improvement of the adjacent territory has been started.

Fourth phase (1, Kryshtaleva Street)

• installation of windows continues (windows on the 3rd floor are completely glassed-in, and window frames on the 2nd, 4th-8th floors are installed);

• masonry up to the 16th floor is ready.

Fifth phase (1-B, Kryshtaleva Street)

• the floor slab of the first floor has been completed.