First phase (9-A, Oksamytova Street)
• the house is commisisoned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• the walls are ready and the work on the entrance groups at the entrance to the second part of the underground parking lot is underway;
Second phase (11-A, Oksamytova Street)
• work on communications has been completed;
• floor cap has been made;
• facade works are underway.
Third phase (1-A, Kryshtaleva Street)
• installation of radiators and work on entrance groups is completed;
• completed work on input groups;
• finishing works in the lobby on the ground floor have been completed;
• improvement of the adjacent territory has been started.
Fourth phase (1, Kryshtaleva Street)
• installation of windows continues (windows on the 3rd floor are completely glassed-in, and window frames on the 2nd, 4th-8th floors are installed);
• masonry up to the 16th floor is ready.
Fifth phase (1-B, Kryshtaleva Street)
• the floor slab of the first floor has been completed.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025