
First phase (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• works on arrangement of fire-prevention systems, electric installation works proceed; completed floor cap in the second part of the underground parking lot.
Second phase (11-A, Oksamytova Street)
• start-up and adjustment works in elevators are finished;
• the arrangement of public usage places continues (installation of windows is completed and facade works are started);
• improvement of the adjacent territory continues;
• installation of balconies on the upper floors has been completed.
Third phase (1-A, Kryshtaleva Street)
• the house is commissioned;
• the arrangement of the adjacent territory around the house has been partially completed.
Fourth phase (1, Kryshtaleva Street)
• plastering works are almost finished (except for the 1st floor);
• roof insulation is completed;
• heating installation is almost completed (except for 15-17 floors);
• work on the floor cap (on the 13th floor) continues.
Fifth phase (1-B, Kryshtaleva Street)
• monolithic frame works on the 9th floor are underway;
• brickwork has been started (on the 2nd floor).
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: SEPTEMBER 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.09.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (SEPTEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.09.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.
26.09.2025