Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
80%
5
stage
40%

Progress in construction RC "Crystal Avenue", April 2020

First stage (9-A, Oksamytova St.)

• the house is commissioned;

• all apartments are sold and partially occupied;

• arrangement of the local area around the house is partially completed.

 

Second stage (11-A, Oksamytova St.)

• monolithic frame work at the 10th floor level is completed;

• external walls up to 9th floor are bricked;

• installation of monolithic stairs is completed at the level of the 9th floor;

• installation of inter-apartment walls of aerated concrete with a layer of mineral wool is completed.

 

Third stage (1 – A, Kryshtaleva St.)

• preparation for the closure of the technical floor;

• monolithic stairs are poured up to the 17th floor;

• brickwork of red aerated concrete reached the 10th floor;

• installation of internal interroom walls, ventilation and chimneys continues inside the house.

 

Fourth stage  (1, Kryshtaleva St.)

• concrete preparation for the foundation is ready;

• preparation for filling the floor slab of the building