First stage (9-A, Oksamytova St.)
• the house is commissioned;
• all apartments are sold and partially occupied;
• arrangement of the local area around the house is partially completed.
Second stage (11-A, Oksamytova St.)
• monolithic frame work at the 10th floor level is completed;
• external walls up to 9th floor are bricked;
• installation of monolithic stairs is completed at the level of the 9th floor;
• installation of inter-apartment walls of aerated concrete with a layer of mineral wool is completed.
Third stage (1 – A, Kryshtaleva St.)
• preparation for the closure of the technical floor;
• monolithic stairs are poured up to the 17th floor;
• brickwork of red aerated concrete reached the 10th floor;
• installation of internal interroom walls, ventilation and chimneys continues inside the house.
Fourth stage (1, Kryshtaleva St.)
• concrete preparation for the foundation is ready;
• preparation for filling the floor slab of the building
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025