Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", April 2023

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed;

Second phase (11-A, Oksamytova Street)

• hall finishing, works on connection of power supply networks, improvement of the territory and waterproofing works are in progress;

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of a ventilated facade (80% ready);

• installation of a wet facade (75% ready);

• gasification of the house (50% ready);

• installation of fire equipment (80% ready).

Fifth phase (1-B, Kryshtaleva Street)

• monolithic works on the 18th floor;

• brickwork on the 9th floor.