Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", August 2020

First stage (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and partially occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• preparatory earthworks for the construction of the second part of the underground parking lot are being completed.

Second stage (11-A, Oksamytova Street)

• works on the monolithic frame are underway at the level of the 17th floor;

• brickwork of external walls of 12-13 floors is executed;

• installation of monolithic stairs is completed at the level of 14 floors;

• installation of windows has started (3rd floor).

Third stage (1-A, Kryshtaleva Street)

• completed all monolithic works;

• completed brickwork;

• completed installation of windows (except for the first two floors), plastering works, preparatory works on electricity and plumbing;

• roofing works have started.

Fourth stage (1, Kryshtaleva Street)

• ready floor slab of the 6th floor