Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", March 2023

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed;

Second phase (11-A, Oksamytova Street)

• hall finishing, works on connection of power supply networks and improvement of the territory are in progress;

• waterproofing works have been started.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of a ventilated facade (75% performed);

• installation of the wet facade (65% performed); 

• gasification of the building has begun (40% complete), installation of firefighting equipment (60% complete).