Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", November 2023

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• installation of outdoor lighting, laying paving slabs, installation and automation of barriers, installation of a fire safety system in the parking lot have been completed

• preparations for planting plants are underway.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of power cables and electrical panels and plastering works on the basement floor have been completed;

• works on decoration of the public usage places (30% ready), installation of public usage places doors (70% ready), installation of internal fire systems (90% ready), installation of air conditioner baskets, installation of elevator equipment, landscaping of the territory are ongoing;

• the arrangement of the fountain area and the installation of equipment in the control room have begun.

Fifth phase (1-B, Kryshtaleva Street)

• the brickwork of the walls is being completed (95% ready);

• arrangement of sewage systems and roof is in progress.