The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• the process of house commissioning and connecting the gas supply is ongoing.
The fifth stage (1-B Kryshtaleva str.)
• facade works are in progress (90% complete), interior finishing and electrical works (15% complete), finishing of the public usage places and staircases (10% complete), installation of elevators (50% complete), installation of apartment doors (50% complete);
• preparations for the installation of boilers and radiators have begun;
• preparations for laying the membrane and the final layer of landscaping are underway in the last part of the underground parking lot.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025