Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
80%

Progress in construction RC "Crystal Avenue", January 2025

The first stage (9-A Oksamytova St.)

• the house is commissioned.

The second stage (11-A Oksamytova St.)

• the house is commissioned.

The third stage (1-A Kryshtaleva str.)

• the house is commissioned.

Fourth stage (1 Kryshtaleva str.) 

• the process of house commissioning and connecting the gas supply is ongoing.

The fifth stage (1-B Kryshtaleva str.)

• facade works are in progress (90% complete), interior finishing and electrical works (15% complete), finishing of the public usage places and staircases (10% complete), installation of elevators (50% complete), installation of apartment doors (50% complete);

• preparations for the installation of boilers and radiators have begun;

• preparations for laying the membrane and the final layer of landscaping are underway in the last part of the underground parking lot.