Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", April 2021

First phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• waterproofing works and backfilling in the second part of the underground parking lot are being performed.

Second phase (11-A, Oksamytova Street)

• facade, plaster works and screed continue;

• construction of communications on apartments is almost completed (works proceed on 16-17 floors).

Third phase (1-A, Kryshtaleva Street)

• radiators (3rd floor) and boilers (11-12 floors) are being installed;

• connection to networks (gas, electricity) continues.

Fourth phase (1, Kryshtaleva Street)

• plumbing work continues;

• work related to flues has been completed.

Fifth phase (1-B, Kryshtaleva Street)

• works on the foundation slab is in progress.