
The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• the process of house commissioning and connecting the gas supply is ongoing.
The fifth stage (1-B Kryshtaleva str.)
• installation of internal gas supply systems, plastering and screed arrangement are completed;
• facade works (90% complete), interior finishing and electrical works, and elevator installation are in progress;
• apartment doors have been ordered;
• waterproofing works are underway in the last part of the underground parking lot.
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: AUGUST 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
31.08.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (AUGUST 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.08.2026
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: AUGUST 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
31.08.2026