Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
85%

Progress in construction RC "Crystal Avenue", June 2025

The first stage (9-A Oksamytova St.)

•  the house is commissioned.

The second stage (11-A Oksamytova St.)

•  the house is commissioned.

The third stage (1-A Kryshtaleva str.)

•  the house is commissioned.

Fourth stage (1 Kryshtaleva str.) 

•  the process of connecting gas and electricity supply on a permanent basis is underway, as well as preparations for signing major contracts.

The fifth stage (1-B Kryshtaleva str.)

•  the main works on finishing of the public usage places and staircases, installation of window and door structures on the 1st and 2nd floors have been completed;

•  facade works (99% complete), internal and electrical works (95% complete), installation of boilers and radiators (85% complete), arrangement of the 1st floor facade, external lighting, irrigation, and landscaping works are in progress;

•  preparations for planting plants and finishing works in the lobby have begun;

•  in the last part of the underground parking lot, landscaping works are underway, preparations for pouring the floor and installing the fire safety system.