First phase (9-A, Oksamytova Street)
• house is commissioned;
Second phase (11-A, Oksamytova Street)
• house is commissioned;
Third phase (1-A, Kryshtaleva Street)
• house is commissioned;
Fourth phase (1, Kryshtaleva Street)
• installation of the pump room has been completed, and water supply has been started;
• works on finishing the hall (95% ready), installation of irrigation (95% ready), installation of radiators and meters (80% ready), finishing works in the fountain bowl are in progress;
• preparations for the building commissioning are underway .
Fifth phase (1-B, Kryshtaleva Street)
• installation of the water supply system has been completed;
• installation of the heat supply system (90% complete), facade works (50% complete), plastering works (60% complete), screed installation (40% complete), and gas supply installation (30% complete) are in progress;
• preparation for interior finishing works has begun;
• the last part of the project is still in the process of pouring the parking lot floor slab (60% complete).
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026