Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", March 2024

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• bushes and flowers have been planted;

•preparation for installation of the children's playground is underway.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

•launching of the elevator equipment has been completed;

•works on finishing the public usage places (75% complete), facade works on the 1st floor (80% complete), finishing the hall, and landscaping works are underway.

Fifth phase (1-B, Kryshtaleva Street)

•sewerage systems have been completed;

•installation of windows (12-16 floors) and roofing (60% complete) is underway;

• electrical installation works on the final stage and monolithic works on the last part of the underground car park have begun.