First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed.
Second phase (11-A, Oksamytova Street)
• facade works are completed;
• installation of outdoor lighting and preparation for planting plants is ongoing.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of the wet facade is completed;
• works on public usage places decor is ongoing (20% ready), doors installation for public usage places (30% ready), installation of internal fire systems (90% ready), installation of power cables and electrical panels (80% ready), landscaping of the territory;
• production of apartment doors has started.
Fifth phase (1-B, Kryshtaleva Street)
• the brickwork of the walls is being completed (95% ready);
• preparation for installation of windows and arrangement of the roof is in progress;
• work on the construction of another underground parking lot has begun. There, the construction of the pit has now been completed and preparations for monolithic works are underway.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026