Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", October 2023

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• facade works are completed;

• installation of outdoor lighting and preparation for planting plants is ongoing.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of the wet facade is completed;

• works on public usage places decor is ongoing (20% ready), doors installation for public usage places (30% ready), installation of internal fire systems (90% ready), installation of power cables and electrical panels (80% ready), landscaping of the territory;

• production of apartment doors has started.

Fifth phase (1-B, Kryshtaleva Street)

• the brickwork of the walls is being completed (95% ready);

• preparation for installation of windows and arrangement of the roof is in progress;

• work on the construction of another underground parking lot has begun. There, the construction of the pit has now been completed and preparations for monolithic works are underway.