Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", February 2021

The Construction Progress of the RC “Crystal Avenue”, February 2021

First phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• waterproofing works in the second part of the underground parking lot are being performed.

Second phase (11-A, Oksamytova Street)

• works on the road to the first house of the RC have been completed near the house.

Third phase (1-A, Kryshtaleva Street)

• works related to water supply and sewerage are being carried out;

• finishing works have been started in public places.

Fourth phase (1, Kryshtaleva Street)

• completed monolithic frame works at the level of the 16th floor;

• brickwork on the 10th floor has been completed.

Fifth phase (1-B, Kryshtaleva Street)

• work on borehole injection piles has been completed.