Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", August 2022

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the local area around the house is partially completed;

• lighting and ventilation systems, parking lot covering, road  marking, and gate installation in the second part of the underground parking lot have been completed.

Second phase (11-A, Oksamytova Street)

• interior finishing on the floors: work was done on 6 floors;

• facade arrangement of the basement floor (300 sq. m. is ready);

• installation of radiators (installed on six floors);

• installation of tiles on cold transitions (70% done);

• installation of suspended ceilings: 2 floors are completed;

• landscaping of the surrounding area: work is completed on an area of 500 square meters;

• works on the installation of lightning protection on the roof, installation of basement waterproofing, installation of entrance groups and commissioning of elevators have been completed.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• partially completed arrangement of the adjacent territory around the house.

Fourth phase (1, Kryshtaleva Street)

• installation of a ventilated facade (10% performed in July);

• arrangement of internal gas supply (20% performed in July);

• installation of the wet facade has begun.

Fifth phase (1-B, Kryshtaleva Street)

• brickwork continues (completed on the 7th floor).