First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the local area around the house is partially completed;
• lighting and ventilation systems, parking lot covering, road marking, and gate installation in the second part of the underground parking lot have been completed.
Second phase (11-A, Oksamytova Street)
• interior finishing on the floors: work was done on 6 floors;
• facade arrangement of the basement floor (300 sq. m. is ready);
• installation of radiators (installed on six floors);
• installation of tiles on cold transitions (70% done);
• installation of suspended ceilings: 2 floors are completed;
• landscaping of the surrounding area: work is completed on an area of 500 square meters;
• works on the installation of lightning protection on the roof, installation of basement waterproofing, installation of entrance groups and commissioning of elevators have been completed.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• partially completed arrangement of the adjacent territory around the house.
Fourth phase (1, Kryshtaleva Street)
• installation of a ventilated facade (10% performed in July);
• arrangement of internal gas supply (20% performed in July);
• installation of the wet facade has begun.
Fifth phase (1-B, Kryshtaleva Street)
• brickwork continues (completed on the 7th floor).
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026