First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed.
Second phase (11-A, Oksamytova Street)
• installation of the playground is underway.
Third phase (1-A, Kryshtaleva Street)
• house is commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• finishing of the public usage places, installation of lamps in the public usage places, installation of railings has been completed;
• works on finishing the hall (80% ready), installation of irrigation (80% ready), installation of radiators and meters (50% ready), installation of a pump room (95% ready), facade arrangement (50% ready) are in progress;
• preparations for water supply have been started.
Fifth phase (1-B, Kryshtaleva Street)
• electrical work has been completed and window installation is almost complete (except for the 1st floor);
• installation of water supply and heating systems (70% complete), facade works (30% complete), plastering works (40% complete), installation of gas supply;
• preparations for the screed have begun;
• works on pouring of the parking lot floor slab continue.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025