Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", July 2024

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• installation of the playground is underway.

Third phase (1-A, Kryshtaleva Street)

• house is commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• finishing of the public usage places, installation of lamps in the public usage places, installation of railings has been completed;

• works on finishing the hall (80% ready), installation of irrigation (80% ready), installation of radiators and meters (50% ready), installation of a pump room (95% ready), facade arrangement (50% ready) are in progress;

• preparations for water supply have been started.

Fifth phase (1-B, Kryshtaleva Street)

• electrical work has been completed and window installation is almost complete (except for the 1st floor);

• installation of water supply and heating systems (70% complete), facade works (30% complete), plastering works (40% complete), installation of gas supply;

• preparations for the screed have begun;

• works on pouring of the parking lot floor slab continue.