Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", September 2023

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• work on connecting power supply networks and preparation for greening of the surrounding area continues;

• the arrangement of retaining walls and the work on the paving of passageways has been completed.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of a ventilated facade (100% ready);

• installation of a wet facade (98% ready);

• gasification of the house (90% ready);

• installed cooling of cold transitions;

• work on the improvement of the territory is ongoing;

• public usage places decoration (5% ready) and production of public usage places doors started;

• preparation for the stair railings installation is underway.

Fifth phase (1-B, Kryshtaleva Street)

• brickwork of walls on the 13th and 18th floors and the roof;

• installation of ventilation channels is completed;

• preparation for installation of windows is in progress.