First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed;
Second phase (11-A, Oksamytova Street)
•hall finishing and works on connecting gas supply networks have been completed;
•works on connection of power supply networks and improvement of the territory are ongoing.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of a ventilated facade (95% ready);
• installation of a wet facade (95% ready);
• gasification of the house (90% ready);
• installation of fire equipment (90% ready);
• work on the improvement of the territory is ongoing;
• installation of doors for public usage (10% ready) and preparation for finishing works has begun.
Fifth phase (1-B, Kryshtaleva Street)
• brickwork of walls on the 11th floor continues.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025