First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed;
Second phase (11-A, Oksamytova Street)
•hall finishing and works on connecting gas supply networks have been completed;
•works on connection of power supply networks and improvement of the territory are ongoing.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation of a ventilated facade (95% ready);
• installation of a wet facade (95% ready);
• gasification of the house (90% ready);
• installation of fire equipment (90% ready);
• work on the improvement of the territory is ongoing;
• installation of doors for public usage (10% ready) and preparation for finishing works has begun.
Fifth phase (1-B, Kryshtaleva Street)
• brickwork of walls on the 11th floor continues.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: SEPTEMBER 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.09.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (SEPTEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.09.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.
26.09.2025