Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", April 2024

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• irrigation has been installed;

• preparations for planting the lawn are underway;

• production of a playground has been launched.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of internal gas supply has been completed;

• works on finishing of the public usage places (85% ready), facade works on the 1st floor (80% ready), installation of radiators, installation of railings (80% ready), finishing of the hall, landscaping works (planting) are in progress;

• preparations for the installation of boilers have begun.

Fifth phase (1-B, Kryshtaleva Street)

• installation of windows (2nd, 3rd, 16th floors), roofing (70% complete), and electrical work is in progress;

• installation of water supply and heating systems has begun;

• preparations for facade and plastering works are underway;

• pouring the foundation slab in the last part of the underground parking lot continues.