Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", July 2020

First stage (9-A, Oksamytova Street)

 • the house is commissioned;

 • all apartments are sold and partially occupied;

 • the arrangement of the adjacent territory around the house has been partially completed;

 • preparatory earthworks for the construction of the second part of the underground parking lot have been started.

Second stage (11-A, Oksamytova Street)

 • completed works on monolithic frame at the level of the 14th floor;

 • brickwork of external walls up to the 11th floor has been made;

 • installation of monolithic stairs is completed at the level of the 10th floor;

 • installation of aerated concrete inter-apartment walls with a layer of mineral wool is completed.

 Third stage (1-A, Kryshtaleva Street)

 • all monolithic works have been completed;

 • brickwork is completed;

 • installation of windows (10th floor), plastering works (5-6 floors), sanitary works and installation of the fire alarm system (the first stage is executed) proceed.

 Fourth stage (1, Kryshtaleva Street)

 • works on monolithic frame on the 4th floor have been completed