Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", July 2021

First phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• concrete works on the entrance groups at the entrance to the second part of the underground parking lot have been completed;

Second phase (11-A, Oksamytova Street)

• installation of apartment doors (3-4 floors) and vestibule doors has started;

• facade and finishing works, installation of elevators proceed.

Third phase (1-A, Kryshtaleva Street)

• improvement of the adjacent territory (laying of paving slabs) continues.

Fourth phase (1, Kryshtaleva Street)

• installation of window frames continues (15th floor);

• plastering works are underway (5-6 floors);

• heating installation has started.

Fifth phase (1-B, Kryshtaleva Street)

• the floor slab of the first floor has been completed.