First stage (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and partially occupied;
• the arrangement of the adjacent territory around the house has been partially completed.
Second stage (11-A, Oksamytova Street)
• completed works on monolithic frame at the level of the 12th floor;
• brickwork of external walls up to the 9th floor has been made;
• installation of monolithic stairs is completed at the level of the 9th floor;
• completed installation of aerated concrete inter-apartment walls with a mineral wool layer.
Third stage (1-A, Kryshtaleva Street)
• all monolithic works have been completed;
• brickwork is completed;
• installation of windows, plumbing and installation of fire alarms continues.
Fourth stage (1, Kryshtaleva Street)
• works on monolithic frame at the level of the 1st floor have been completed
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026