Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", June 2020

First stage (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and partially occupied;

• the arrangement of the adjacent territory around the house has been partially completed.

Second stage (11-A, Oksamytova Street)

• completed works on monolithic frame at the level of the 12th floor;

• brickwork of external walls up to the 9th floor has been made;

• installation of monolithic stairs is completed at the level of the 9th floor;

• completed installation of aerated concrete inter-apartment walls with a mineral wool layer.

Third stage (1-A, Kryshtaleva Street)

• all monolithic works have been completed;

• brickwork is completed;

• installation of windows, plumbing and installation of fire alarms continues.

Fourth stage (1, Kryshtaleva Street)

• works on monolithic frame at the level of the 1st floor have been completed