The first phase (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and partially occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• the overlapping in the second part of the underground parking lot is being prepared.
The second phase (11-A, Oksamytova Street)
• completed brickwork of the walls, except for the first floor;
• completed electrical work, the Internet;
• plastering of walls and slopes has been performed on 2–14 floors;
• the floor screed has been made on 3-8 floors.
The third phase (1-A, Kryshtaleva Street)
• doors, floor screed and drains installation continues;
• facade works are underway;
• finishing works of common areas have been completed.
The fourth phase (1, Kryshtaleva Street)
• monolithic frame works are underway at the level of the 12th floor;
• brickwork of walls at the level of 2–4 floors has been started.
The fifth phase (1-B, Kryshtaleva Street)
• pit development is underway.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: SEPTEMBER 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.09.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (SEPTEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.09.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.
26.09.2025