Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", November 2020

The first phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and partially occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• the overlapping in the second part of the underground parking lot is being prepared.

The second phase (11-A, Oksamytova Street)

• completed brickwork of the walls, except for the first floor;

• completed electrical work, the Internet;

• plastering of walls and slopes has been performed on 2–14 floors;

• the floor screed has been made on 3-8 floors.

The third phase (1-A, Kryshtaleva Street)

• doors, floor screed and drains installation continues;

• facade works are underway;

• finishing works of common areas have been completed.

The fourth phase (1, Kryshtaleva Street)

• monolithic frame works are underway at the level of the 12th floor;

• brickwork of walls at the level of 2–4 floors has been started.

The fifth phase (1-B, Kryshtaleva Street)

• pit development is underway.